

云陽(yáng)長(zhǎng)江大橋:
云陽(yáng)長(zhǎng)江大橋是三峽工程二期蓄水前重慶開(kāi)建的最后一橋。大橋起于北岸云陽(yáng)新縣城,止于南岸磐石鎮(zhèn),全橋長(zhǎng) 1278.6米 ,主橋長(zhǎng) 637米 ,引橋長(zhǎng)為 641.6米 ,主橋跨徑組臺(tái)為132+318+ 187米 ,單箱雙室空心截面塔柱主墩,雙江鎮(zhèn)岸引橋?yàn)?× 30米 簡(jiǎn)支T梁,盤(pán)石鎮(zhèn)岸引橋?yàn)?× 50米 簡(jiǎn)支T梁。該工程于2002年11月開(kāi)工建設(shè),2005年9月28日竣工通車(chē)。
Yuyang Yangtze River Bridge:
Yunyang Yangtze River Bridge is the last bridge built in Chongqing before Three Gorges Project Phase II impoundment. The bridge starts from Yunyang New County on the north bank and ends at Panshi Town on the south bank. The full bridge is 1278.6m long, main bridge is 637m long and approach bridge is 641.6m long and main bridge span combination is 132+318+ 187 m. It uses single-box two-chamber hollow section pylon main pier, the approach bridge on the bank of Shuangjiang Town is 9× 30m and uses simply supported T beam and the approach bridge on the bank of Panshi Town is 7×50m and uses simply supported T beam . The project was commenced in November, 2002 and completed and open to traffic on September 28, 2005.